Capital phasing table — years 0 to 10 (two-site smart farm)
Purpose
Lay out infrastructure and equipment spend on a 0–10 year horizon for the two-site grazing-led strategy family, with placeholders for amounts and financing. Complements East Tennessee two-site farm business plan — capital plan and CAPEX, OPEX, and enterprise sequencing — two-site constraint.
Key decisions supported
| Decision |
Table use |
| When to spend on fence vs telemetry |
Row timing + gate column |
| Home vs farm CAPEX |
Site column |
| Debt vs cash |
Source column—no silent credit card leverage |
| Stop if gate fails |
Link Gate ID to Validation backlog — before major spend |
Phasing map (business plan Phases 0–4)
| Yr (approx) |
Business plan phase |
Capital theme |
| 0–1 |
0–1 |
No-regret, intel, pilot |
| 2–4 |
2 |
MVP production infra + herd or contracts |
| 5–7 |
3 |
Scale or second stream |
| 8–10 |
4 |
Salary architecture, hardening |
Capital table — years 0–10 (fill)
Legend: Site = HOME | FARM | BOTH · Src = CASH | FIN | GRANT | LEASE (equipment) · Gate = prerequisite ID
| Yr |
Quarter (opt) |
Category |
Item |
Site |
Est $ |
Src |
Gate / trigger |
Irreversible? |
| 0 |
|
Legal / maps |
Surveys, boundary, access clarity |
BOTH |
$_ |
CASH |
G0 |
Partially |
| 0 |
|
Comms |
Homelab baseline / backup |
HOME |
|
|
|
|
| 1 |
|
Land intel |
Soil, water tests, fence audit |
FARM |
|
|
V-land |
|
| 1 |
|
Telemetry pilot |
One I/O path (see Instrumentation priority matrix) |
FARM |
|
CASH |
I-manual |
|
| 2 |
|
Water |
Develop / extend distribution |
FARM |
|
FIN? |
G1 |
Yes |
| 2 |
|
Fence |
Perimeter / interior MVP |
FARM |
|
FIN? |
G1 |
Yes |
| 2 |
|
Livestock |
Herd or contract buy-in |
FARM |
|
|
margin |
|
| 3–4 |
|
Handling |
Corral / load-out MVP |
FARM |
|
|
|
|
| 3–4 |
|
Transport |
Truck/trailer class upgrade |
BOTH |
|
|
|
|
| 5–7 |
|
Scale |
Add paddocks, water, herd |
FARM |
|
|
G2 |
|
| 5–7 |
|
Telemetry |
Expand sensors within OPEX cap |
FARM |
|
|
|
|
| 8–10 |
|
Optimization |
Cold chain, direct marketing assets |
BOTH |
|
|
G3 |
|
Add rows; do not pre-fill $_ without quotes.
Financing caution (checklist)
Known / assumed / open
| Class |
Content |
| Known |
Phased investment + selective financing stated in plan |
| Assumed |
Off-farm income subsidizes early years |
| Open |
FSA / lender terms; exact EQIP eligibility |