Loads register — known, estimated, unknown (two sites)
Purpose: Single register for electrical and major duty-cycled energy loads at SITE_HOME and SITE_FARM so Farm on-site power system, Utility baseline, and business-plan execution share one table—without mixing in parcel or soil facts.
Package: Local evidence package — East Tennessee two-site.
Business plan: East Tennessee two-site farm business plan (package) — energy targets stay in package pages; here: site-specific load lines.
Epistemic classes
| Class |
Meaning |
| Measured |
Clamp meter, utility interval data, inverter log |
| Estimated |
Nameplate × duty cycle—show math in notes column |
| Assumption |
Planning default from equipment plan—replace |
| Unknown |
Not yet identified or metered |
Electrical loads (master table)
| Site |
Load ID |
Description |
Fact class |
V / phase |
A or W (steady) |
Start / surge |
Hours/day (season) |
Priority (1=critical) |
Blocks |
| SITE_HOME |
H-L-001 |
Example: well pump |
Unknown |
TBD |
TBD |
TBD |
TBD |
TBD |
Inverter/charger sizing |
| SITE_HOME |
H-L-002 |
Example: HVAC |
Unknown |
TBD |
TBD |
TBD |
TBD |
TBD |
Battery kWh |
| SITE_FARM |
F-L-001 |
Example: irrigation pump |
Unknown |
TBD |
TBD |
TBD |
TBD |
TBD |
Solar pump controller |
| SITE_FARM |
F-L-002 |
Example: barn lights |
Unknown |
TBD |
TBD |
— |
TBD |
TBD |
Circuit layout |
Add rows; do not invent amperages—Unknown until measured.
Thermal / non-electric energy (where relevant)
| Site |
Load ID |
Description |
Fact class |
Fuel / source |
Duty |
Blocks |
| SITE_HOME |
H-T-001 |
Heat / DHW |
Unknown |
TBD |
TBD |
Electrification vs propane |
| SITE_FARM |
F-T-001 |
Water heating for parlor / wash |
Unknown |
TBD |
TBD |
Solar thermal vs electric |
Simultaneity and diversity (planning)
| Scenario |
Fact class |
Assumed overlapping loads |
Notes |
Blocks |
| Winter evening peak (home) |
Assumption |
TBD |
Replace with measured stack |
Whole-home backup |
| Irrigation + barn (farm) |
Unknown |
TBD |
Field verify |
Generator vs grid upgrade |
Decision gates
| Decision |
Blocked until |
| Inverter kW |
Surge + continuous for worst-case overlapping measured loads |
| Battery kWh |
Measured overnight + irrigation window overlap |
| Grid service upgrade |
Utility demand history + planned new loads |