Pilot and recon checklists — first 24 months (two-site smart farm)
Parent plan: Validation and pilot plan — first 24 months (East Tennessee two-site)
Execution dossier (read first): Hub · Master checklist (priority P0–P3) · Decision memo.
Wishful-thinking trap: Checking a row is not validation. Evidence means verifiable artifacts (file, letter, third-party readout, dated photo set) that survive skepticism—see hostile internal review §7.
Use as copy-paste into a spreadsheet or print; date and initial each completed row in the field.
Land intelligence and mapping
| # |
Item |
Owner |
Target date |
Done |
Evidence pointer |
| L1 |
MAP_AUTHORITY file/layer chosen (name: ___) |
|
|
|
|
| L2 |
NRCS soil survey pulled for 120 ac footprint |
|
|
|
|
| L3 |
Wet / steep areas walked + photos in album ___ |
|
|
|
|
| L4 |
Paddock or field segments numbered on map |
|
|
|
|
| L5 |
Fence segments walked; photo per major segment |
|
|
|
|
| L6 |
No-build / sensitive areas noted (streams, sinkholes) |
|
|
|
|
Infrastructure reconnaissance
| # |
Item |
Owner |
Target date |
Done |
Evidence pointer |
| I1 |
All water points located on map (well, pond, trough) |
|
|
|
|
| I2 |
Flow or recovery test notes (method: ___) |
|
|
|
|
| I3 |
Pump / panel labels verified by two people |
|
|
|
|
| I4 |
Dry season stress observation (if applicable) |
|
|
|
|
| I5 |
Primary access route driven after heavy rain |
|
|
|
|
| I6 |
Gate IDs match asset registry convention |
|
|
|
|
First business experiments
| # |
Item |
Owner |
Target date |
Done |
Notes |
| B1 |
12 auction sale bills collected (species: ___) |
|
|
|
|
| B2 |
Processor call log — name, dates, distance |
|
|
|
|
| B3 |
Haul quote or DIY cost range per head |
|
|
|
|
| B4 |
Lease comps filed (if lease path ) |
|
|
|
|
| B5 |
Kill / pivot rule written if B1–B3 fail threshold |
|
|
|
|
First telemetry experiments
| # |
Item |
Owner |
Target date |
Done |
Notes |
| T1 |
30-day manual water check log completed |
|
|
|
|
| T2 |
Cell / LTE screenshots at pins (tank / gate ) |
|
|
|
|
| T3 |
One pilot sensor ID ___ mounted at ___ |
|
|
|
|
| T4 |
Trip count before vs after pilot (4 weeks ) |
|
|
|
|
| T5 |
Triage hours / month estimated |
|
|
|
|
| T6 |
Kill decision documented if T5 > benefit |
|
|
|
|
First labor and workflow tests
| # |
Item |
Owner |
Target date |
Done |
Notes |
| W1 |
8-week hour log (family roles ) |
|
|
|
|
| W2 |
One surge window captured (dates ) |
|
|
|
|
| W3 |
Weekly rhythm doc updated after W1 |
|
|
|
|
| W4 |
Two-site trip log — purpose coded |
|
|
|
|
| W5 |
Coverage gap → hire / neighbor row added ? Y/N |
|
|
|
|