Execution gates — Phase 0–1 (East Tennessee two-site)¶
Purpose¶
Turn the narrowed Phase 0–1 plan into an execution-gate system: what may start, what stays pilot-only, and what must not proceed to production posture (irreversible CAPEX, herd scale, privileged remote control, financed infrastructure).
Relationship to existing IDs
- G1–G3 and V1–V12 remain on
Validation backlog and decision gates. This page adds EG- prefixed gates that decompose Phase 0–1 readiness by domain so a team can see why G1 is or is not honest. - Fin-G* family thresholds live on
Execution gates — financial thresholds—this page does not invent dollar values or percentage constants; it requires documented family/chosen thresholds where those pages use placeholders.
Pilots vs production (definitions)
| Stance | Meaning |
|---|---|
| Pilot allowed | Bounded time/$/scope; kill criteria written before start; observe-first where actuation exists; no implied scale. |
| Production allowed | Sustained operating posture: repeatable visits, named coverage, finance-grade evidence where money moves, no open fail rows for the decision class. |
Evidence routing: Local evidence package — East Tennessee two-site, Field verification program — Phase 0–1 (Claxton and Demory), Claxton and Demory — missing data register.
1. Local evidence readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-LEV-1 | Register hygiene | Without an honest gap list, desk maps become fake certainty | Pilot: Every Phase 0–1 row in missing data register has status (open / measured / deferred-with-next-step) + owner. Production: No G1-class item (legal use, access, water, stocking driver) remains “assumed” without dated field plan or written waive |
Any G1-class row blank or orphan (no owner, no next step) | Desktop research, county pulls, scheduled field visits | Production fence/water/herd decisions that depend on a hidden gap |
| EG-LEV-2 | Field verification cadence | Phase 0–1 is narrowed toward measured truth | Pilot: Field verification program kickoff recorded (T0-relative) with which sections run first. Production: Dated logs exist for both sites for the minimum sections named in dossier “Ready for execution” §C |
Program not started after calendar slip without explicit reschedule | Promotion of measurements into local evidence package tables |
Treating county/WSS summaries as parcel-complete for CAPEX |
Pilot vs production: Pilot allows scheduled work and partial logs; production requires dated evidence or explicit waive for the specific claim.
2. Site / infrastructure readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-SITE-1 | Legal use + access | Bad title/use/access voids economics | Pilot: V8 started (zoning/ag-structure path documented as letter, ticket, or defensible memo). V2 started (water rights question list to attorney or agency). Production: No open legal contradiction on intended Phase 2 enterprise on ~120 ac operating area; year-round access plan exists (maintain, agreement, or honest seasonal limit) | Silent assumption that “ag use” equals your intended ops | Pilot equipment leases, small fence patches, market probes | G1 and EG-LEV production bars; financed perimeter/water |
| EG-SITE-2 | Field-safe infrastructure | Injury, stuck trucks, and false capacity drive margin lies | Pilot: V3 walk started (photo + map pins). Production: V3 album + map tied to rotation/handling plan; worst-case access route logged once in bad weather or documented inability | No photos / no map authority label | Pilot soil/water sampling visits | Owned herd scale; heavy earthwork without lane/drainage peer review |
Pilot vs production: Pilot allows recon and small fixes; production requires closed legal/access story and field infrastructure truth for the bet size.
3. Off-grid power readiness (SITE_FARM default)¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-PWR-1 | Power domain truth | Telemetry and gateways compete with welfare loads on battery | Pilot: Off-grid operational decision rules read; DR-1 class question (“metered or bracketed network + always-on electronics load vs autonomy”) has named owner + due. Production: Bracket or measure exists or explicit deferral caps new always-on RF/WAN loads |
New always-on IP radios / second farm WAN while DR-1-class question open | Pilot single-gateway + one RF class pilot | Production multi-node RF mesh, second Starlink/CPE farm install, HaLow scale |
| EG-PWR-2 | Degraded posture | Off-grid is time in brownout behavior | Pilot: Off-grid degraded modes skimmed; manual welfare check path stated in one paragraph. Production: Ops agrees which pumps/gates are manual-first when SoC low / WAN down |
Remote dashboard treated as welfare proof | Pilot observe-only sensors on Pcrit loads | Remote actuation on water/gate class; production “NOC from phone” story |
Pilot vs production: Pilot = one bounded power story + observe-first; production = measured or bracketed headroom for chosen always-on stack.
4. Connectivity and trust-bar readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-NET-1 | WAN role explicit | Starlink/LTE must not hide primary dependency | Pilot: Connectivity strategy — Claxton & Demory read; per-site WAN role captured in one sentence each (primary / backup / deferred). Production: Local-first paths exist for P1 telemetry class when WAN absent (Local-first / WAN-optional — Demory) |
Farm requires constant WAN for basic stock/water safety checks | Pilot LTE/Starlink trial installs per capital sequencing | Production “cloud is SoR” for welfare decisions |
| EG-NET-2 | Trust bar for remote privilege | VPN ≠ safety | Pilot: Observability, secrets, and trust bar minimum trust bar checklist exists in family runbook (copy OK). Production: All trust-bar items true for the specific remote actions contemplated (patch, break-glass, actuator API) |
Privileged remote path enabled before bar items true | Read-only dashboards; pilot push metrics | Production remote actuation; break-glass admin from internet |
Pilot vs production: Pilot allows read-only remote visibility if manual welfare path holds; production remote control requires EG-NET-2 production pass plus Automation stop rules.
5. Sensor readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-SNS-1 | Manual baseline (G8 family) | Automation without baseline is theater | Pilot: G8 path chosen (which asset); paper or spreadsheet baseline started. Production: G8-equivalent complete per validation — before major spend G8 row (log without remote control language) |
Baseline skipped “because sensors shipping” | Pilot one sensor class install | Second sensor class; alerts-as-SoR; production actuation |
| EG-SNS-2 | Single pilot scope | Sprawl burns labor on triage | Pilot: Exactly one pilot cluster documented (device class + uplink + owner + kill threshold triage h/wk). Production: Pilot reviewed against Instrumentation ROI or killed with reason |
Parallel pilots without written exception | Pilot expansion within cluster | Fleet rollout; production “instrument everything” |
Pilot vs production: Aligns with Farm sensor architecture — Demory and Sensor checklist matrix — Demory—one green path first.
6. Platform / backup / observability readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-PLT-0 | Stack scope declared | Gates do not apply to stacks you are not running | Declared: No homelab/k3s in Phase 0–1 or Pi/k3s pilot scope doc (nodes, services, non-goals) | Implicit “we’ll fix in prod” k3s | If no stack: backup/observability rows N/A (other evidence still applies). If pilot stack: EG-PLT-1 applies | Confusion about which EG-PLT rows apply |
| EG-PLT-1 | Backup + restore + observe (when stack exists) | k3s without restore is single incident from total loss | Pilot: One restore drill or documented failure to schedule with date. Production: RPO/RTO stated in family terms (hours/days—not dollar amounts); Kubernetes platform backup/DR — Pi k3s Longhorn P0/P1 checklist green for in-scope nodes |
No restore test and no dated plan | Pilot extra workloads on cluster | Production Longhorn/HA expansion; treating cluster as SoR without restore proof |
Pilot vs production: Platform doctrine package; production implies repeatable drills and named on-call for patch/secret hygiene.
7. Labor readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-LAB-1 | Hour budget evidence | Plans collapse in surge | Pilot: V11 started (any multi-week slice). Production: V11 8+ weeks including one stress/surge window per dossier Ready §B | Weekly grid treated as fact before log | Pilot extra recon trips | Production surge enterprises; G1 production claim |
| EG-LAB-2 | Overload coverage | Two-site tax becomes emergency-only | Pilot: Coverage matrix shows holes named. Production: Each critical hole has neighbor / hire / defer row non-empty or enterprise scope cut |
“We’ll figure it out” for calving/hay/escape class | Pilot market/auction attendance | Production commitments needing daily presence at 120 |
Pilot vs production: Pilot accepts documented holes; production requires closed coverage or reduced scope.
8. Financial readiness¶
| ID | Gate | Why it matters | Pass criteria | Fail criteria | Unlocks | Blocked if fail |
|---|---|---|---|---|---|---|
| EG-FIN-1 | Insurance reality | One loss wipes years | Pilot: V9 quotes collected. Production: Binder reviewed with agent; exclusions/limits understood (notes OK) | Quote-only treated as covered | Pilot small sales / lease probes | Production visitor-facing ops; financed equipment where lender requires proof |
| EG-FIN-2 | Numeric policy exists | Stop rules without numbers are decorative | Pilot: Vision stop-rule template copied locally. Production: Placeholders N (key-person weeks), D% (debt vs gross revenue), and operating reserve months (per Capital plan / Execution gates — financial thresholds) are filled in the family ledger—wiki holds structure, not invented constants |
Blank thresholds during Phase 2 CAPEX ask | Pilot bookkeeping pattern | Production term debt; salary narrative |
Pilot vs production: No invented financial constants in-repo—EG-FIN-2 production pass is “filled elsewhere, linked or cited privately”, not numbers invented in markdown.
Composite: what each stance allows¶
| Decision class | Minimum gate posture |
|---|---|
| Begin desk / county / calls / templates | No EG production requirement; follow Decision memo Approved now |
| Pilot spend / installs / small CAPEX | Relevant EG pilot passes for that domain + decision memo pilot rules |
| Production spend (G1-class: fence MVP, water development, herd scale, financed infra, remote actuation) | G1 on validation backlog and production bars for EG-LEV-1, EG-SITE-1, EG-LAB-1, EG-FIN-1; plus domain production bars for power/connectivity/sensors/platform if that domain is in scope |
Mapping — EG gates to V / G references¶
| EG gate | Primary V / G / doc hooks |
|---|---|
| EG-LEV-1 / EG-LEV-2 | Register + field program; supports G1 honesty |
| EG-SITE-1 | V2, V8; G1 legal/access |
| EG-SITE-2 | V3; G1b-class physical access |
| EG-PWR-1 / EG-PWR-2 | DR-* / degraded docs; blocks production RF/WAN sprawl |
| EG-NET-1 / EG-NET-2 | Connectivity strategy + trust bar; pairs R16 mitigations |
| EG-SNS-1 / EG-SNS-2 | G8, instrumentation matrix, stop rules |
| EG-PLT-0 / EG-PLT-1 | Platform decision memo + backup/DR page |
| EG-LAB-1 / EG-LAB-2 | V11, coverage matrix |
| EG-FIN-1 / EG-FIN-2 | V9, vision/capital numeric policy |
Related¶
First 90 days — operator packet (East Tennessee two-site)— Weeks 1–12 pilot runbook aligned to EG pilot barsPhase 0–1 operator burden review — East Tennessee two-site (hostile)— skeptical stack view of recurring/surge/invisible load vs EG gatesExecution dossier — Phase 0–1 (hub)Validation backlog and decision gatesBusiness plan integration revision audit (2026-04)East Tennessee two-site farm business plan (package)