Purpose

Extend two-site degraded-mode thinking for SITE_FARM (Demory) when power and WAN fail independently or together — without duplicating Manual fallback prose .

Doctrine package: Off-grid systems doctrine package — Demory.

Topology views : Off-grid farm execution topology — Demory (Mermaid) .

mermaid stateDiagram-v2 [*] --> Nominal Nominal --> N1 : WAN down only Nominal --> Pstress : SOC / PV fault N1 --> N2 : add power stress Pstress --> N2 : add WAN loss note right of N2 : N2 — paper rounds; battery-backed critical only


Failure classes (farm-specific)

Class Symptoms Safe assumption Operator response
P1 — Deep battery SOC / load shed Inverter sheds non-critical ; some radios drop Telemetry silence ≠ “ fine ” at the water . Physical rounds ; disable non-critical RF if policy says so .
P2 — PV / charge fault Reduced daily Wh budget Starlink and high duty cameras may need to stay off until SOC recovers . Runbook : Runbook — power loss at remote site .
N1 — WAN down , power OK No cloud ; mesh / LAN may still work Same as global LEO WAN impaired row on Manual fallback . Runbook — broker or backhaul down .
N2 — WAN + power stress (both ) No egress ; some nodes dark Only battery-backed critical paths matter . Paper rounds ; genset policy if installed (TBD ) .**

What must still work (policy)

  • Welfare interlocks that do not require cloud .
  • At least one local way to know tank / gate state (sight , float , local indicator ) .
  • Offline records discipline for anything that feeds books .

  • Coordinating with Claxton (SITE_HOME ) , vendors , or weather when you choose to burn Wh on CPE .
  • Decision to drive for Tier-1 animal or water risk — policy beats dashboard .