Decision memo — Phase 0–1 execution (East Tennessee two-site)¶
Purpose¶
One memo for: what the family may do now, what is pilot-only, and what is forbidden until validation gates pass. Execution means pilot-grounded action—not premature scale.
Gates: Validation backlog (G1–G3), Validation — before major spend (G1–G8 where applicable).
Governance / doctrine ledger: Business plan integration revision audit (2026-04) (what the canonical plan now assumes about evidence vs execution). Privileged remote access stays behind Observability, secrets, and trust bar — homelab / farm edge trust bar—not “VPN exists.”
Execution gates (EG): Execution gates — Phase 0–1 (East Tennessee two-site) — pilot allowed vs production allowed by domain; use before widening pilots or claiming G1 passed.
Approved for action now (no gate waiver)¶
Definition: Low cash outlay; reversible; does not commit herd scale, perimeter fence MVP, financed equipment, or remote actuation.
| Category | Allowed |
|---|---|
| Governance | Stop rules posted; hour log started; one canonical map authority file |
| Land intel | NRCS pulls; walks and photos; segment notes |
| Legal / use | County / zoning calls; scoped attorney consult (fee per budget) |
| Markets | Sale bill collection; processor calls; haul math |
| Water | Manual check logs; water points on map |
| Access | Bad-weather drives; photo logs |
| Telemetry | Manual baseline logs (G8 path); cell screenshots at pins; read-only comms tests |
| Labor | Weekly rhythm doc; two-site trip purpose logging |
Approved only for pilot (bounded scope + kill criteria)¶
Definition: Small dollar or time box; owner named; kill criteria written before start; no implicit scale.
| Category | Pilot rules |
|---|---|
| Telemetry | One sensor class + one uplink path—Instrumentation priority matrix; stop if triage exceeds benefit per Automation stop rules |
| Business | Market probes only until V5/V6 have first-pass evidence; small/short lease pilot if aligned to Recommended enterprise strategy |
| Infra | Spot fence repairs for safety/escape only—not full perimeter MVP without G1 |
| Labor | Surge window test with coverage matrix update |
Forbidden until validation gates pass¶
| Forbidden | Until |
|---|---|
| Full perimeter fence MVP / major water development CAPEX | G1 + major-spend rows (water rights G3 as applicable) |
| Owned herd above documented conservative capacity | V4 + G1 + V6 path credible |
| Financed equipment (loader, hay line, truck class) | Hours/year proof + custom-hire quote per Remediation §3; V9 as applicable |
| Telemetry fleet, multi-zone cameras, remote actuation | G8 manual baseline; PA- proofs for actuation (Smart tech strategy); NS- stop rules |
| Second major enterprise stream | V11 surge covered + margin proof (Phase 3-class—see validation backlog G2) |
| Phase 4–style salary replacement claims | G3 per validation backlog |
Insurance illusion: A quote or binder PDF is not proof of coverage. V9 pass means reviewed with the agent for named perils, exclusions, equipment limits, and umbrella layer—not a checkbox.
Sign-off (family — fill in tracker)¶
| Field | Value |
|---|---|
| T0 (execution start) | |
| Review date for this memo | |
| Named owner for gate evidence |