Decision memo — Phase 0–1 execution (East Tennessee two-site)

Purpose

One memo for: what the family may do now, what is pilot-only, and what is forbidden until validation gates pass. Execution means pilot-grounded action—not premature scale.

Gates: Validation backlog (G1–G3), Validation — before major spend (G1–G8 where applicable).

Governance / doctrine ledger: Business plan integration revision audit (2026-04) (what the canonical plan now assumes about evidence vs execution). Privileged remote access stays behind Observability, secrets, and trust bar — homelab / farm edge trust bar—not “VPN exists.”

Execution gates (EG): Execution gates — Phase 0–1 (East Tennessee two-site) — pilot allowed vs production allowed by domain; use before widening pilots or claiming G1 passed.


Approved for action now (no gate waiver)

Definition: Low cash outlay; reversible; does not commit herd scale, perimeter fence MVP, financed equipment, or remote actuation.

Category Allowed
Governance Stop rules posted; hour log started; one canonical map authority file
Land intel NRCS pulls; walks and photos; segment notes
Legal / use County / zoning calls; scoped attorney consult (fee per budget)
Markets Sale bill collection; processor calls; haul math
Water Manual check logs; water points on map
Access Bad-weather drives; photo logs
Telemetry Manual baseline logs (G8 path); cell screenshots at pins; read-only comms tests
Labor Weekly rhythm doc; two-site trip purpose logging

Approved only for pilot (bounded scope + kill criteria)

Definition: Small dollar or time box; owner named; kill criteria written before start; no implicit scale.

Category Pilot rules
Telemetry One sensor class + one uplink path—Instrumentation priority matrix; stop if triage exceeds benefit per Automation stop rules
Business Market probes only until V5/V6 have first-pass evidence; small/short lease pilot if aligned to Recommended enterprise strategy
Infra Spot fence repairs for safety/escape only—not full perimeter MVP without G1
Labor Surge window test with coverage matrix update

Forbidden until validation gates pass

Forbidden Until
Full perimeter fence MVP / major water development CAPEX G1 + major-spend rows (water rights G3 as applicable)
Owned herd above documented conservative capacity V4 + G1 + V6 path credible
Financed equipment (loader, hay line, truck class) Hours/year proof + custom-hire quote per Remediation §3; V9 as applicable
Telemetry fleet, multi-zone cameras, remote actuation G8 manual baseline; PA- proofs for actuation (Smart tech strategy); NS- stop rules
Second major enterprise stream V11 surge covered + margin proof (Phase 3-class—see validation backlog G2)
Phase 4–style salary replacement claims G3 per validation backlog

Insurance illusion: A quote or binder PDF is not proof of coverage. V9 pass means reviewed with the agent for named perils, exclusions, equipment limits, and umbrella layer—not a checkbox.


Sign-off (family — fill in tracker)

Field Value
T0 (execution start)
Review date for this memo
Named owner for gate evidence