First 90 days — operator packet (East Tennessee two-site)

What this is

A bounded, field-facing runbook for the first 12 weeks after T0—pilot execution only. It does not replace the narrative arc on First 90 days — Phase 0–1; it packages what the operator actually does each week, what evidence must exist, and when to stop.

Pilot justification (explicit): Pilot work is justified when T0 is set on the Decision memo, the family stays inside Approved now + Approved only for pilot, and EG rows are pursued at pilot bar—not production / G1 posture (Execution gates — Phase 0–1). Do not treat this packet as permission for Forbidden rows on the memo.

Aligns with: narrowed Phase 0–1 scope · EG gates · Field verification program — Phase 0–1 · Operator burden review (hostile) · decision memo.

Out of scope here: months 4–24 detail, Phase 2 CAPEX, herd scale, salary narrative—use First 12 months after day 90.


Weekly priorities (weeks 1–12)

Rule: Each week, pick at most one “hard” slice (long drive + heavy field) unless surge—Operator burden review.

Week Priority theme Ship this week (max 3 outcomes)
1 T0 + books + stop rules T0 date on memo; hour log week 1 started; vision stop-rule template copied locally
2 Legal surface + map authority V8 started (ticket/letter path); one canonical map layer name; trip purpose codes started
3 Labor truth V11 week 3 logged; coverage matrix holes named (no heroics)
4 Checkpoint A Decision checkpoints; adjust week 5–8 if overload
5 Land intel (cheap) V1 desktop + first Demory walk tied to field program §1; V3 photos started
6 Water + access V2 question list moving; water points on map (I1); bad-weather access log once
7 Markets paper V5 first sale bills; V6 first processor call log row
8 Checkpoint B EG-LEV pilot pass honest? NS-2 triage budget real? Trim pilots if not
9 Insurance + haul V9 quotes collected; B3 haul bracket documented as range, not fantasy
10 Connectivity (pilot) V10 pin screenshots started; WAN placement/obstruction log per first-90-days connectivity table
11 G8 + comms stability Manual water (or chosen G8 asset) log in progress or complete; no second sensor class
12 Checkpoint C + handoff Day-90 “done enough” items from First 90 days § End of day 90 checklist; schedule first 12 months review

Field verification tasks (mapped)

Execute rows from Field verification program in this order of emphasis—not all sections every trip.

Week band Demory (SITE_FARM) emphasis Claxton (SITE_HOME) emphasis
1–4 §1 orienting + boundary/fence walk starter; §2 access lane photo §4–5 utility / ISP / OSSS truth path started (desktop + any field)
5–8 §3 drainage / sediment eyes after rain if possible; §1 fence segments deepen Same + §6 gateway location paper only unless pilot already approved
9–12 §4–5 power / pump spot checks without new always-on RF; §7 sensor mount sites scout only §6 homelab / WAN power intent for CPE

Cadence: Follow field program § “Bundling”—every Demory trip bundles access + one infra slice.


Infrastructure setup tasks (90-day cap)

Task Site Done when Gate / stop
Primary route bad-weather log Demory One logged attempt or documented deferral with date Supports EG-SITE-2 pilot
Water points on map Demory All known points pinned + Unknown list V2 / I1
CPE / WAN power intent Claxton Ticket or two-person shutdown story on paper Connectivity table Days 31–60 row
Spot fence / escape fix Demory Only safety per memo pilot infra row—not perimeter MVP Memo Forbidden guard

Sensor / network / platform tasks (90-day cap)

Task Done when Stop
Declare stack scope EG-PLT-0: written “no k3s” or “k3s pilot = {nodes}” If undeclared, freeze cluster feature creep
G8 manual baseline Asset chosen; paper/spreadsheet log started week ≤8; complete by T0+120d if not by day 90 No sensor install without baseline path
One RF / one gateway pilot Matches DR-5 class scope; no second farm WAN / HaLow while DR-1 open CS-5
V10 cell at pins Notebook/screenshots started week ≤10 No “telemetry drives trips” claim without V10 track
Triage time budget H_TRIAGE_BUDGET_WK set in ROI worksheet or family equivalent NS-2

Documentation updates required

Artifact Owner By
Missing data register rows Ops lead Weekly status + owner (EG-LEV-1)
Local evidence package tables Ops lead After each field visit bundle
Hour log (V11) Named family Weekly through week ≥8 inside 90d window
WAN / reliability notebook Tech lead First entry by day 30; weekly by day 90
Pilot one-pager (one sensor class, kill threshold) Tech lead Before any install (EG-SNS-2)

Stop conditions (non-exhaustive)

Freeze or cut the week’s plan if any apply—then document and reschedule:

  • Decision memo Forbidden row would be violated by the next action.
  • EG pilot fail in a domain you are about to spend in (e.g. register orphan rows before claiming “ready for contractor talk”).
  • Automation stop rules NS-1–NS-3, CS-1, CS-4, CS-5 after one remediation attempt.
  • Operator burden review collision week: Tech lead and Field lead same person and both had surge—drop one pilot thread.
  • R17 signal: triage + field + off-grid same week with no coverage—invoke coverage matrix or cancel non-welfare work.

Evidence collection requirements

By Minimum evidence Feeds
Day 30 V8 path started; V11 ≥4 weeks; map authority; one Demory field visit log (field program); WAN obstruction/placement log started EG-SITE-1 pilot, EG-LEV-2 pilot
Day 60 V1 + V3 usable for conversation (not perfect); V5/V6 first rows; V10 notebook started V tasks; first-90-days days 31–60
Day 90 First-90-days end checklist satisfied or dated slip with which item carries to T0+120d Handoff to First 12 months

Decision review checkpoints

When Review questions (family) Outcome
End week 4 Still inside memo Approved / pilot only? Any Forbidden pressure? EG-LEV pilot rows owned? Adjust weeks 5–8 scope
End week 8 V11 on track for 8 weeks total? NS-2 triage budget real? Exactly one telemetry pilot thread? Kill or defer sensor/WAN extras
End week 12 First-90-days end checklist met or slips dated? G8 done or scheduled by T0+120d? No G1 / production composite claimed without evidence? Written plan for days 91–180; handoff to First 12 months